Sakuto
Offtaker of Electricity
Chugoku Electric Power Company
Scale of Power Generation
257.7 MWdc
Location
Mimasaka-shi, Okayama-ken
EPC Contractor
JGC
Project Finance
Sumitomo Mitsui Trust Bank, Limited
Syndication Banks
Date of Facility Certification (METI)
March 16, 2015
Commencement of Construction
April 2017
Date of Commercial Operation
Q3 2019
Status
Under construction

Sakuto is simply massive in scale: 258MWdc and 750,000 PV modules, spanning the equivalent of 765 football fields. Built on a closed golf course and two other large areas, Sakuto required moving eight million cubic meters of earth and will take 2.5 years to finalize. Once complete, it will be the largest project in Japan.